Drainage at Backworth Primary School

Request:

Could I request the amount that was paid using public funds for the installation 
of drainage to be implemented week commencing 19th February 2024 to the 
West Boundary of Backworth Park Primary School and East Boundary of Hotspur 
North.

Response:

The drainage works within the grounds of Backworth Park Primary was 
undertaken in two parts:


Part 1, completed in February 2024 cost £2,760 including VAT